Key takeaways
- Each shop drawing must be reviewed against the most recent approved design and engineering computations before it can be released.
- Take special care to look at the connections, base plates, and anchor bolts, which is where the problems usually begin.
- The erection sequence and lifting details should be reviewed during approval rather than when the steel arrives on site.
- Ensure that all comments are clear and have sheet references, and get each comment closed out before the final approval.
What are PEB shop drawings and why do they matter?
PEB shop drawings are fabrication drawings that provide all the member, plate, connection, bolt, weld, and accessory details required to manufacture a pre-engineered building. They interpret the engineer's design and prepare instructions that can be used by the fabricator to cut, drill, and assemble. When the fabricator utilizes these drawings, any errors that are in the drawings are likely to be transferred to the steel itself.
Pre-engineered buildings are especially favored for use in warehouses, manufacturing sites, distribution centers, aircraft hangars, and agricultural operations. Their attraction is speed and efficiency. Those benefits rely on the quality of the drawings; a set of clean drawings allows the shop to work smoothly, allows the erector to install the pieces in the order they should go in, and allows the owner to rely on the project schedule.
However, shop drawings are also responsible. After the fabricator begins work according to an approved drawing, the approver is at least as responsible for the drawing as the fabricator. So approval should never be an afterthought at the end of a hectic week! It is a technical review that requires time, a clear checklist, and documented comments.
Who should review PEB shop drawings?
Typically, there are several roles in approval, each of which looks at the drawings differently. The structural engineer validates design intent. The fabricator confirms buildability in the shop. The erector has verified that it is safe to assemble pieces on the site. The project manager verifies scope, changes, and the time frame.
The right people up front decrease late surprises. Engineers identify load path problems, fabricators detect cutting and welding limitations, and the erectors discover access problems that are frequently undocumented on drawings. The owners who rely on the PEB detailing services in USA and have a requirement to have a detailer's review before the engineer of record's sign-off.
- Structural Engineer: verifies that the drawings accurately represent approved loads, codes, and design assumptions.
- Fabricator: Assesses the ability to cut, drill, and assemble members, plates, and welds in a shop.
- Erector: Examines sequencing, access, temporary bracing, and lifting points.
- Owner or project manager: Confirms scope, revision control, and the approval schedule.
Which standards should guide the review?
The check is not based on personal taste alone because it has a set of standards to which it is compared. In the United States, the majority of PEB projects are directed in accordance with the building code requirements, loading standards, and steel fabrication and erection specifications. To ensure that the reviewers are aware of which versions are covered, older versions may be found in the contract documents.
Common references include:
- Local jurisdictions' adoption of building code provisions establishing design framework.
- The minimum design loads, including wind, snow, and seismic actions, are defined in the ASCE 7 code.
- AISC 360, the specification for structural steel buildings, member design and connections.
- AISC 303, the code for Fabrication or Erection of steel buildings and bridges, establishes expectations for fabrication and erection.
- The MBMA Metal Building Systems Manual is a design and detailing reference that is widely used for metal building design and detailing.
- AWS D1.1, the structural welding code for steel, governs weld quality and procedures.
Moreover, a drawing that meets the design requirements but fails to meet the required standard must be corrected. Remember to note down the edition and clause in your comments so the detailer can respond accurately.
What are the key checks before approving steel fabrication?
It is important that member sizes and dimensions are confirmed to be consistent with the design, connections are complete and buildable, that bolts and welds are consistent with specified grades and sizes, and that base plates, anchor rods, and accessories match foundation and cladding layout prior to approving steel fabrication. All checks should be followed back to the approved design paper.
Start with large elements and work towards the small. Begin with overall geometry, then move on to members, connections, and finally the little items that seem to cause a lot of trouble in the shop.
How do you verify member sizes and dimensions?
Start by installing the basic members of the frame, including the rafters, columns, and endwall framing. Check section sizes, depths, lengths, and material grades against the approved member schedule. The risk of one incorrect section cascading through all the sections that rely on it makes this step a point of scrutiny.
Then, verify building geometry. Check spacing of bays, height of eaves, slope of roof, column line offsets, and length and width of the building against the architectural set. Be careful of grid line references. One of the most costly mistakes that can be made after the steel is delivered to the site is the mismatch of the gridlines of the shop drawings and the foundation plan drawing.
Useful items to check include:
- Section sizes, depths, and material grades are consistent with the member schedule.
- The spacing of bays, eave height, and roof slope are in line with the architectural drawings.
- The layout of the foundation and the gridlines or column offsets are the same.
- Camber, Cut lengths, and splice locations are clearly indicated.
Are connection details correct and buildable?
The most common shop drawing issues are connections. Check all moment, base, eave, and ridge connections and purlin or girt connections. Be sure to verify that plate thicknesses, bolt pattern, edge distance, and weld size are fully specified. If these details are missing or not clear, the fabricator must guess, and rework will occur.
Buildability is important as well as being correct. Verify if bolts can be torqued with the required wrench or impact tool and if welds will be accessible in shop orientation, and to determine if there are clearances to allow adjoining members to fit together. A connection that may seem correct on paper but is not able to be assembled results in delays in the erection process and can lead to unexpected changes in the field.
How should bolts, welds, and base plates be reviewed?
Start with bolts. Verify diameters, grades, and quantities for all connections, and compare with the bolt schedule. Verify if pretensioning or snug-tight specifications are included as applicable. Any inconsistencies with the bolt size, like a bolt dimension given in one view but not the other, should be marked as such right away.
Welds are no exception to this. Examine and verify weld symbol size, length, and type, and verify if each weld is shop or field. Ensure that the welding procedure requirements in project specifications are referred to. Lack of clear or complete weld information is a serious quality problem – it should not be left to the fabricator to guess at.
Base plates and anchor rods must be treated with great care since they establish a connection between the steel structure and the foundation. The dimensions, thickness, hole sizing, anchor rod layout, and positioning should be double-checked with respect to the foundation and other civil drawings. The proper projection, embedment, and template have to be confirmed, since even a deviating offset can otherwise lead to unplumbed column installations.
What should be checked in panel layout and accessories?
The drawings for panel layouts indicate the arrangement of roofing and wall panels, the patterns of fasteners employed, and the installation of all trims and flashings as well as the placement of any openings. Ensure that the lengths of the panels are the same as the dimensions of the building, and that the doors, windows, and vents are situated correctly. It is important to note that some gaps can only be detected after the installation when water is leaking through them.
Accessories require the same level of attention. Sag rods, bracing components, purlin clips, gutters, downspouts, canopies, and mezzanine supports are all part of the steel installation. Confirm the number, place, and type of connections of accessories as outlined in the main frame. Accessories are typically designed last, and this is one of the most frequent causes of missing from the list of required materials.
How can fabrication drawing reviews reduce rework?
A thorough drawing review helps to minimize rework before the first cut is made. The drawings should be accurate and complete so that the shop does not have to ask questions to cut, punch, and weld the correct pieces, and the project is not corrected at an unnecessary and expensive cost. It is generally very cheap to review early compared to fixing them after steel is fabricated, shipped, or erected.
The advantage of using steel fabrication drawings services in USA is that many times the most significant savings are realized by picking up small errors early since there is a multiplication effect. A wrong hole location can impact dozens of pieces. A mislabelled piece mark may end up delivering the wrong part to site, and the absence of a note could delay an entire erection sequence. Clear, checked drawings are good for the budget and the schedule!
Rework also comes with its price tag. Fabricators might need to rework parts, erectors may need to wait for parts to be corrected, and inspectors may require additional time to make sure parts are changed. As the number of handoffs increases, so does the amount of overhead and delay. Careful review before release ensures that the project continues to move forward.
Why does connection detailing matter for approval?
Connection detailing helps members to understand how loads are transferred through the structure and how easily it can be put together. Good connection details are clearly written and provide enough information for the fabricator to do their job without having to decipher the information. One of the primary causes of rework, delays, and changes in the field for steel works is poor connection detailing.
Connections are the places where the forces of connection are applied, and therefore should be viewed most closely when approved. A detailer with design intent knowledge and shop practice knowledge is able to identify issues before cutting any steel. Many project teams therefore seek steel connection detailing services in USA when they require an independent review of the complete set of connections.
Double-check all connections with member and bolt sheets. Make sure each connection referred to in the frame elevations is in the detail set. Ensure the clip, cleat, or end plate fits the member flange width and depth. These checks are time-consuming, but they reveal errors that cause the most problems when getting up.
How do erection drawings support approval?
Shop drawings instruct the fabricator with regard to what to construct, and erection drawings instruct the crew with regard to how to erect it on site. A full comparison is made of the two sets. Ensure that the piece marks, assembly sequence, and lifting points on the shop drawings are consistent with the erection drawings and erection plan.
Teams who use steel erection drawings services in USA have found that erection planning results in problems that aren't identified in the shop drawings. Once adjacent members are in place, a bolt might be able to be reached only from one side. It may be necessary to temporarily brace a frame before it can stand safely. If these conditions are identified at approval, they will avoid costly field fixes and safety concerns.
Erection checks worth adding to every review:
- The same piece marks should be used on shop and erection drawings.
- For heavy pieces, lifting points and member weights are indicated.
- Stability and bracing needs are determined.
- There is good access to and clearance for bolting operations.
- The erection sequence facilitates stable and progressive assembly.
What common mistakes appear in shop drawings?
Some of the errors are recurring in metal building packages. If you know where they typically go, the review process will be quicker and more targeted. The table below shows the high-priority areas.
| Review Area | What to Verify | Common Error |
|---|---|---|
| Member sizes | Section, depth, length, and grade match the design | Wrong section or outdated revision |
| Connections | Plate thickness, bolts, and welds are complete | Missing or conflicting details |
| Bolts | Diameter, grade, quantity, and tightening notes | Mismatch between detail and bolt schedule |
| Welds | Size, length, type, and shop or field designation | Unclear or missing weld symbols |
| Base plates | Dimensions, holes, and anchor rod layout | Offset from the foundation plan |
| Accessories | Location, quantity, and attachment points | Items left out of the material list |
Revision control is another frequent problem. Drawings may be modified based on comments, and the superseded sheets may be included in the package. Make sure to mention the revision letter or date on each sheet and request a revision log from the detailer that explains what and why the revisions have been made. Many of these issues can be captured by making a quick comparison with the last approved set.
Which red flags should stop an approval?
While some findings may not necessarily need to be redesigned, the approval process should be halted on others until they are addressed. If you see these warning signs, keep an eye on them:
- Sizes of the member that differ from the approved design schedule
- Connections shown without complete bolt, weld, or plate information
- Attach anchor rods that are incompatible with the foundation plan
- Unresolved comments that were left in from a previous review cycle
- Changes in the load, code, or building geometry that have not been explained
- Piece marks duplicated across different members
If a red flag occurs, note it, return the package, and ask for a corrected submission. Sponsoring drawings where conflicts are known moves the risk to people with less information and less time to resolve the issue.
How do you approve shop drawings step by step?
To ensure consistency across projects, a repeatable sequence allows for reviews to take place in the same manner. Write these words in order:
- Please be sure you have the most recent revision of the approved design package and the right shop drawing set.
- Ensure overall geometry, gridlines, and general arrangement are correct as per architectural and foundation drawings.
- Check member timetable, section sizes, and material grades.
- Check every connection type for completeness, consistency, and buildability.
- Verify cross-check bolts, welds, and base plates to specifications and schedules.
- Match panel layouts and openings to the architectural package, and match accessories.
- Check erection sequence, lifting points, and bracing notes.
- Wait until all comments are closed and the corrected set is verified to be released.
How should review comments be communicated?
Remove comments to move toward resubmission. Every comment must contain the sheet number that the comment is on, the location on the sheet, the problem being addressed, and the reference to support the correction (design schedule or code clause). Don't leave cryptic messages such as “check connection.” Rather, record on sheet S-12 “Confirm bolt diameter at the eave connection is the same as bolt schedule.”
Additionally, tone matters too. A specific, respectful comment will prompt a prompt response from the detailer. Organize comments in groups, distinguish between critical comments and minor editing notes, and follow up on comments until they are closed. Everyone is on the same list thanks to a shared tracking log.
Closing line
The process of approving PEB shop drawings plays an important quality role in any steel project. A complete review assures that the steel belongs in the right shape, consisting of proper sections and joining elements, correctly bolted and welded, and properly base plated, panelled and outfitted before work begins in the shop.
Regardless of whether you conduct the reviews on your own or seek assistance from outside consultants, the main task is to be consistent. For more complicated projects, consider using the PEB detailing services from Ambari Consultant in the USA to protect the quality of steel from the very first drawing to the erection of the structure.
Frequently asked questions
-
What is the most important check before approving PEB shop drawings?
Drawing confirmation with the latest revision of the drawing approved is most important because all other information is based on the approved design revision. -
How long does a shop drawing review usually take?
Depending on the size and complexity of the building, review can take a few days, and sometimes more, and then must be resubmitted. -
Can shop drawings be approved without an engineer’s review?
Rules of approval vary with every contract and each jurisdiction. However, the structural engineer is the one to assure the drawings represent the approved design. -
Why do shop drawings often contain errors?
Mistakes usually happen due to late changes in the design, obsolete revisions, lack of coordination, or manual transfer of measurements between sets of drawings.